Recently,
ZHONGHAIKE 1, the first cable laying and repairing vessel undertaken by CHI(Shanghai),
was delivered at CHI(Shanghai) Marine Heavy Duty Terminal. The vessel is the
most advanced self-powered cable laying vessel in China, with a hull length of
108.56 metres, a width of 24 metres, a total cable loading capacity of 3,000
dwt, and a full load displacement of 10,705 dwt. Equipped with advanced
electric drive system, the vessel has a total output power of 10,260 kW and DP2
power positioning technology, which enables it to operate stably in any sea
area in the world, with strong wind and wave resistance and unlimited
navigation area. CHI(Shanghai) focused on three aspects: structural
modification, precision installation of cable-laying equipment and mooring test
of special functional equipment. During the fabrication of the aft cable inlet
section, the project team compiled official drawings within two weeks through
on-site mapping, modelling and repeated comparison and correction with the
site, and completed the fabrication and CCS acceptance of four sections within
26 days. The precision installation of cable-laying equipment is another major
difficulty in the transformation of ZHONGHAIKE 1. The project team closely
negotiated and communicated with the equipment manufacturers, which finally
ensured the smooth installation and commissioning of all the equipment.
|