Originally
scheduled for 21-day routine repairs, the CS Harmony vessel lost 4 days due to
port congestion caused by severe weather. CHI(Shanghai) completed hydraulic
system repairs within 10 days, including 3 winch motors, 2 pump station motors,
9 hatch valve actuators, and 3 hatch opening motors. Facing compressed
deadlines at the 300,000-ton Emeishan Dock, workers completed diverter cowling
installation and non-destructive testing in 52 hours – 20% faster than standard
schedules. The 15.3-ton cowling was installed as a single unit, with all welds
passing magnetic particle/ultrasonic testing on first inspection. CHI(Shanghai)
will continue optimizing processes to enhance repair capabilities while
maintaining its client-focused approach for vessel delivery and operational
efficiency.
|