Dalian
COSCO SHIPPING Heavy Industry has completed repairs on the bulk carrier
"Shun Fu Da", enabling the vessel to depart two days ahead of
schedule. Despite a tight timeline and unexpected additional work, the project
team delivered high-quality repairs, earning praise from the shipowner.
The
scope of work included renewing inner bottom plates in multiple cargo holds,
cleaning fuel oil tanks, and overhauling key machinery like the main engine and
generators. During the dry-docking, a survey revealed cracks posing a leakage
risk on the outer bottom plate of a ballast tank. The project management team
promptly executed an emergency plan, efficiently mobilizing resources to
complete the critical repair.
The
fuel tank cleaning was finished within one day, and the outer plate renewal
utilized continuous operations to meet the undocking deadline.
The
shipowner's technical superintendent highly praised the team's expertise and
efficiency, expressing interest in future repair collaborations.
|